A plant works 5 days a week, 2 shifts a day. Each 8-hour shift has two 15-minute tea breaks and a 30-minute lunch. Weekly demand is 1,350 units. What is the takt time?
- A. 93.3 seconds
- B. 200.0 seconds
- C. 186.7 seconds
- D. 213.3 seconds
Correct answer: C. 186.7 seconds
Available per shift = 480 − 60 = 420 min. Weekly = 420 × 2 × 5 = 4200 min. Takt = 4200 ÷ 1,350 = 3.1111 min = 186.7 s. Deducting only lunch gives 4,500/1,350 min = 200 s; ignoring all breaks gives 213.3 s.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Tasks (time in s; immediate predecessors): A 8 (–), B 5 (A), C 6 (A), D 9 (B), E 4 (C), F 7 (D, E), G 3 (F). The cycle time is 12 s. Tasks…
- A machine needs a 60-minute setup before each batch and then 2 minutes per unit. Downstream demand is 27 units per hour. What is the…
- A process has a throughput of 50 units per hour and a flow time of 3 hours. If a WIP cap reduces average work-in-process to 100 units…
- A distributor has annual sales of ₹64 crore, cost of goods sold of ₹48 crore and an average inventory (at cost) of ₹6 crore. Using a…
- Products P and Q share two machines, each available 480 min/day. P needs 3 min on M1 and 4 min on M2; Q needs 5 min on M1 and 2 min on M2…
- Station A takes 10 min per unit and Station B takes 12 min per unit. After Station B, 20% of units fail inspection and go back through…