A plant works 5 days a week, 2 shifts a day. Each 8-hour shift has two 15-minute tea breaks and a 30-minute lunch. Weekly demand is 1,350 units. What is the takt time?

  1. A. 93.3 seconds
  2. B. 200.0 seconds
  3. C. 186.7 seconds
  4. D. 213.3 seconds

Correct answer: C. 186.7 seconds

Available per shift = 480 − 60 = 420 min. Weekly = 420 × 2 × 5 = 4200 min. Takt = 4200 ÷ 1,350 = 3.1111 min = 186.7 s. Deducting only lunch gives 4,500/1,350 min = 200 s; ignoring all breaks gives 213.3 s.