Tasks (time in s; immediate predecessors): A 8 (–), B 5 (A), C 6 (A), D 9 (B), E 4 (C), F 7 (D, E), G 3 (F). The cycle time is 12 s. Tasks are assigned to stations using the 'longest eligible task first' rule. What is the efficiency of the resulting line?

  1. A. 70.0%
  2. B. 30.0%
  3. C. 76.4%
  4. D. 87.5%

Correct answer: A. 70.0%

Assignment: S1 {A} = 8; S2 {C, B} = 11; S3 {D} = 9 (E no longer fits); S4 {E, F} = 11; S5 {G} = 3. Five stations, so efficiency = 42 ÷ (5 × 12) = 70%. 87.5% assumes the theoretical minimum of ⌈42/12⌉ = 4 stations; 76.4% uses the largest station load (11 s) instead of the cycle time.