Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
A machine needs a 60-minute setup before each batch and then 2 minutes per unit. Downstream demand is 27 units per hour. What is the smallest batch size that lets this machine keep up with demand?
- A. 135
- B. 243
- C. 270
- D. 30
Correct answer: C. 270
Capacity with batch B = B ÷ (60 + 2B) units per minute. Set it equal to 27/60 = 0.45: B = 0.45(60 + 2B) = 27 + 0.9B → 0.1B = 27 → B = 270. Note that even an infinite batch cannot exceed 30 units/hr (1 per 2 min).
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A process has a throughput of 50 units per hour and a flow time of 3 hours. If a WIP cap reduces average work-in-process to 100 units…
- A distributor has annual sales of ₹64 crore, cost of goods sold of ₹48 crore and an average inventory (at cost) of ₹6 crore. Using a…
- Products P and Q share two machines, each available 480 min/day. P needs 3 min on M1 and 4 min on M2; Q needs 5 min on M1 and 2 min on M2…
- Station A takes 10 min per unit and Station B takes 12 min per unit. After Station B, 20% of units fail inspection and go back through…
- A retailer sells ₹30 lakh a month at a 25% gross margin (on sales) and carries an average inventory of ₹45 lakh at cost. Holding cost is…
- Jobs arrive at 10 per hour (M/M/1). Option A: a server who handles 12 jobs/hr, costing ₹200/hr. Option B: a server who handles 15 jobs/hr…