A machine needs a 60-minute setup before each batch and then 2 minutes per unit. Downstream demand is 27 units per hour. What is the smallest batch size that lets this machine keep up with demand?

  1. A. 135
  2. B. 243
  3. C. 270
  4. D. 30

Correct answer: C. 270

Capacity with batch B = B ÷ (60 + 2B) units per minute. Set it equal to 27/60 = 0.45: B = 0.45(60 + 2B) = 27 + 0.9B → 0.1B = 27 → B = 270. Note that even an infinite batch cannot exceed 30 units/hr (1 per 2 min).