Station A takes 10 min per unit and Station B takes 12 min per unit. After Station B, 20% of units fail inspection and go back through Station B once (rework takes the full 12 minutes and always succeeds). What is the line's output in an 8-hour shift?

  1. A. 48.0 units
  2. B. 33.3 units
  3. C. 40.0 units
  4. D. 32.0 units

Correct answer: B. 33.3 units

Each good unit needs 1.2 passes at B: 1.2 × 12 = 14.4 min. B's capacity = 60/14.4 = 4.167 units/hr (A: 6/hr), so B is the bottleneck. Output = 4.167 × 8 = 33.3 units. 40 ignores rework; 32 treats the 20% as scrap.