Management & CommerceHardOps MT · Supply chain · MBA placement pattern

Jobs arrive at 10 per hour (M/M/1). Option A: a server who handles 12 jobs/hr, costing ₹200/hr. Option B: a server who handles 15 jobs/hr, costing ₹300/hr. Each job in the system (waiting or in service) costs ₹100 per hour. Which option is cheaper, and what is its total hourly cost?

  1. A. Option B, ₹500/hr
  2. B. Option A, ₹617/hr
  3. C. Option B, ₹433/hr
  4. D. Option A, ₹700/hr

Correct answer: A. Option B, ₹500/hr

L = λ/(μ − λ). A: L = 10/2 = 5 → 200 + 500 = ₹700. B: L = 10/5 = 2 → 300 + 200 = ₹500. B is cheaper. Using Lq (queue only) instead of L gives ₹433 for B, but the cost is charged on every job in the system.