Jobs arrive at 10 per hour (M/M/1). Option A: a server who handles 12 jobs/hr, costing ₹200/hr. Option B: a server who handles 15 jobs/hr, costing ₹300/hr. Each job in the system (waiting or in service) costs ₹100 per hour. Which option is cheaper, and what is its total hourly cost?
- A. Option B, ₹500/hr
- B. Option A, ₹617/hr
- C. Option B, ₹433/hr
- D. Option A, ₹700/hr
Correct answer: A. Option B, ₹500/hr
L = λ/(μ − λ). A: L = 10/2 = 5 → 200 + 500 = ₹700. B: L = 10/5 = 2 → 300 + 200 = ₹500. B is cheaper. Using Lq (queue only) instead of L gives ₹433 for B, but the cost is charged on every job in the system.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- In the Theory of Constraints, which scheduling method paces the whole plant to the bottleneck, protects it with a time buffer and releases…
- Planned production time is 480 minutes, of which 60 minutes are lost to breakdowns. The ideal cycle time is 0.5 min/unit. The machine…
- Monthly sales of a product were 120, 135, 150 and 141 units (oldest first). What is the 3-month moving-average forecast for the next month?
- Sales were 200 (Jan), 220 (Feb) and 250 (Mar). Using a weighted moving average with weights 0.5, 0.3 and 0.2, the heaviest weight on the…
- Last period's forecast was 500 units and actual demand was 540 units. With exponential smoothing and α = 0.3, what is the next forecast?
- The forecast for period 1 was 100. Actual demand in periods 1, 2 and 3 was 110, 95 and 120. Using exponential smoothing with α = 0.2, what…