Annual demand is 66,000 good units. Each unit needs 12 minutes of machine time. Plants run 250 days a year, 2 shifts of 8 hours, with 85% machine efficiency, and 4% of units started are scrapped. How many machines are needed?

  1. A. 3
  2. B. 4
  3. C. 5
  4. D. 6

Correct answer: C. 5

Units to start = 66,000 ÷ 0.96 = 68,750. Hours needed = 68,750 × 12/60 = 13,750. Effective hours per machine = 250 × 2 × 8 × 0.85 = 3,400. Machines = 13,750 ÷ 3,400 = 4.04 → 5. Ignoring scrap gives 13,200 ÷ 3,400 = 3.88 → 4.