Management & CommerceHardOps MT · Supply chain · MBA placement pattern
For the same line (work content 61 s, cycle time 18 s), precedence constraints force the planner to use 5 stations. What is the balance delay?
- A. 18.7%
- B. 32.2%
- C. 15.3%
- D. 67.8%
Correct answer: B. 32.2%
Efficiency = work content ÷ (stations × cycle time) = 61 ÷ (5 × 18) = 67.8%. Balance delay = 1 − efficiency = 32.2%. 15.3% is the delay with 4 stations; 18.7% wrongly uses the longest task (15 s) as cycle time.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A loan-processing centre receives 120 applications per week and has on average 360 applications in process. Management wants the average…
- A serial line has three stages. Stage 1: capacity 100 units/hr, yield 95%. Stage 2: capacity 90 units/hr, yield 90%. Stage 3: capacity 85…
- A single-server help desk (M/M/1) receives 12 requests per hour and can serve 15 per hour. What is the average time a request waits in the…
- A single-window ticket counter (M/M/1) has an arrival rate of 18 per hour and a service rate of 24 per hour. What is the probability that…
- Customers arrive at a single drive-through window at 20 per hour (M/M/1). Management wants the average wait in the queue (before ordering)…
- A diagnostic clinic sees 30 patients per hour. Every patient passes registration (on average 4 patients there) and a doctor (on average 6…