For the same line (work content 61 s, cycle time 18 s), precedence constraints force the planner to use 5 stations. What is the balance delay?

  1. A. 18.7%
  2. B. 32.2%
  3. C. 15.3%
  4. D. 67.8%

Correct answer: B. 32.2%

Efficiency = work content ÷ (stations × cycle time) = 61 ÷ (5 × 18) = 67.8%. Balance delay = 1 − efficiency = 32.2%. 15.3% is the delay with 4 stations; 18.7% wrongly uses the longest task (15 s) as cycle time.