A loan-processing centre receives 120 applications per week and has on average 360 applications in process. Management wants the average processing time cut to 1.5 weeks without changing the arrival rate. By how many applications must average work-in-process fall?

  1. A. 120
  2. B. 240
  3. C. 90
  4. D. 180

Correct answer: D. 180

Current W = 360 ÷ 120 = 3 weeks. Target WIP = 120 × 1.5 = 180. Reduction = 360 − 180 = 180 applications.