A loan-processing centre receives 120 applications per week and has on average 360 applications in process. Management wants the average processing time cut to 1.5 weeks without changing the arrival rate. By how many applications must average work-in-process fall?
- A. 120
- B. 240
- C. 90
- D. 180
Correct answer: D. 180
Current W = 360 ÷ 120 = 3 weeks. Target WIP = 120 × 1.5 = 180. Reduction = 360 − 180 = 180 applications.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A serial line has three stages. Stage 1: capacity 100 units/hr, yield 95%. Stage 2: capacity 90 units/hr, yield 90%. Stage 3: capacity 85…
- A single-server help desk (M/M/1) receives 12 requests per hour and can serve 15 per hour. What is the average time a request waits in the…
- A single-window ticket counter (M/M/1) has an arrival rate of 18 per hour and a service rate of 24 per hour. What is the probability that…
- Customers arrive at a single drive-through window at 20 per hour (M/M/1). Management wants the average wait in the queue (before ordering)…
- A diagnostic clinic sees 30 patients per hour. Every patient passes registration (on average 4 patients there) and a doctor (on average 6…
- A machine is available for 480 minutes a day. Product A needs 4 minutes and product B 6 minutes on it. Daily demand is 50 units of A and…