Management & CommerceModerateOps MT · Supply chain · MBA placement pattern

An assembly line must produce 1,600 units in 480 productive minutes per day. The six tasks take 10, 12, 8, 15, 7 and 9 seconds. What is the theoretical minimum number of workstations?

  1. A. 3
  2. B. 5
  3. C. 4
  4. D. 6

Correct answer: C. 4

Takt (cycle) time = 480 × 60 ÷ 1,600 = 18 s. Work content = 61 s. Minimum stations = ⌈61 ÷ 18⌉ = ⌈3.39⌉ = 4. Rounding down to 3 is the classic error: stations must be rounded up.