Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
An assembly line must produce 1,600 units in 480 productive minutes per day. The six tasks take 10, 12, 8, 15, 7 and 9 seconds. What is the theoretical minimum number of workstations?
- A. 3
- B. 5
- C. 4
- D. 6
Correct answer: C. 4
Takt (cycle) time = 480 × 60 ÷ 1,600 = 18 s. Work content = 61 s. Minimum stations = ⌈61 ÷ 18⌉ = ⌈3.39⌉ = 4. Rounding down to 3 is the classic error: stations must be rounded up.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- For the same line (work content 61 s, cycle time 18 s), precedence constraints force the planner to use 5 stations. What is the balance…
- A loan-processing centre receives 120 applications per week and has on average 360 applications in process. Management wants the average…
- A serial line has three stages. Stage 1: capacity 100 units/hr, yield 95%. Stage 2: capacity 90 units/hr, yield 90%. Stage 3: capacity 85…
- A single-server help desk (M/M/1) receives 12 requests per hour and can serve 15 per hour. What is the average time a request waits in the…
- A single-window ticket counter (M/M/1) has an arrival rate of 18 per hour and a service rate of 24 per hour. What is the probability that…
- Customers arrive at a single drive-through window at 20 per hour (M/M/1). Management wants the average wait in the queue (before ordering)…