Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
A three-stage process: Stage 1 has one machine taking 6 min per unit; Stage 2 has two identical machines in parallel, each taking 15 min per unit; Stage 3 has one machine taking 5 min per unit. What is the maximum output in an 8-hour shift?
- A. 80
- B. 32
- C. 64
- D. 96
Correct answer: C. 64
Capacities per hour: Stage 1 = 60/6 = 10, Stage 2 = 2 × 60/15 = 8, Stage 3 = 60/5 = 12. The bottleneck is Stage 2 at 8 units/hour, so output = 8 × 8 = 64. Ignoring the parallel machine gives 4 × 8 = 32.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A distribution centre holds an average of 6,000 units and ships 1,200 units per week. Assuming 52 weeks a year, what is its annual…
- An assembly line must produce 1,600 units in 480 productive minutes per day. The six tasks take 10, 12, 8, 15, 7 and 9 seconds. What is…
- For the same line (work content 61 s, cycle time 18 s), precedence constraints force the planner to use 5 stations. What is the balance…
- A loan-processing centre receives 120 applications per week and has on average 360 applications in process. Management wants the average…
- A serial line has three stages. Stage 1: capacity 100 units/hr, yield 95%. Stage 2: capacity 90 units/hr, yield 90%. Stage 3: capacity 85…
- A single-server help desk (M/M/1) receives 12 requests per hour and can serve 15 per hour. What is the average time a request waits in the…