Management & CommerceModerateOps MT · Supply chain · MBA placement pattern

A three-stage process: Stage 1 has one machine taking 6 min per unit; Stage 2 has two identical machines in parallel, each taking 15 min per unit; Stage 3 has one machine taking 5 min per unit. What is the maximum output in an 8-hour shift?

  1. A. 80
  2. B. 32
  3. C. 64
  4. D. 96

Correct answer: C. 64

Capacities per hour: Stage 1 = 60/6 = 10, Stage 2 = 2 × 60/15 = 8, Stage 3 = 60/5 = 12. The bottleneck is Stage 2 at 8 units/hour, so output = 8 × 8 = 64. Ignoring the parallel machine gives 4 × 8 = 32.