Management & CommerceHardBig 4 tax · CA Foundation · MBA placement pattern
A mill's broken crankshaft is given to a carrier to take to the makers as a pattern. The carrier is told nothing about the mill being idle without it, and delivers late. Can the mill owner recover the profits lost during the delay?
- A. Yes, all losses caused by the breach are recoverable
- B. No: the lost profit was neither natural nor contemplated
- C. Yes, but only half, as both parties were at fault
- D. Only if the carrier was negligent in transporting the crankshaft
Correct answer: B. No: the lost profit was neither natural nor contemplated
Hadley v Baxendale: damages cover losses arising naturally from the breach or that both parties contemplated when contracting. Special circumstances not communicated make the loss too remote.
More Taxation & Business Law questions
- A contract states that ₹5 lakh is payable on breach. One party breaks it; the other's actual loss is ₹2 lakh. Under Section 74, what can…
- On 1 March, A tells B he will not deliver the goods due on 1 June. What is B's position?
- B agreed to buy 1,000 units at ₹500 each but refused delivery on the due date, when the market price was ₹440. The seller resold a month…
- A hires a hall for a concert, but the hall is destroyed by fire, through no one's fault, before the concert date. What happens to the…
- A owes B ₹1 lakh. A, B and C agree that B will accept C as his debtor instead of A. This is:
- A publisher commissions A to write a book for a series for ₹50,000. After A has written half the book, the publisher abandons the series…