A mill's broken crankshaft is given to a carrier to take to the makers as a pattern. The carrier is told nothing about the mill being idle without it, and delivers late. Can the mill owner recover the profits lost during the delay?

  1. A. Yes, all losses caused by the breach are recoverable
  2. B. No: the lost profit was neither natural nor contemplated
  3. C. Yes, but only half, as both parties were at fault
  4. D. Only if the carrier was negligent in transporting the crankshaft

Correct answer: B. No: the lost profit was neither natural nor contemplated

Hadley v Baxendale: damages cover losses arising naturally from the breach or that both parties contemplated when contracting. Special circumstances not communicated make the loss too remote.