Agriculture & Rural DevelopmentHardNABARD Grade A
Under MGNREGA rules, delay compensation is 0.05% of the unpaid wages per day of delay beyond the stipulated period. Wages of Rs 24,000 are delayed by 20 days beyond that period. The compensation payable is:
- A. Rs 2,400
- B. Rs 12
- C. Rs 24,000
- D. Rs 240
Correct answer: D. Rs 240
0.05% x 24,000 = Rs 12 per day, times 20 = Rs 240; Rs 2,400 wrongly uses 0.5%.
Practise more Rural Development, ARD & ESI (NABARD) questionsRural Development, ARD & ESI (NABARD): notes and key points
More Rural Development, ARD & ESI (NABARD) questions
- Under the MGNREGA Schedule I, the share of works by value to be executed through Gram Panchayats is at least:
- Under PMAY-G, 10,000 houses are sanctioned in plain areas at the unit assistance of Rs 1.20 lakh with a 60:40 Centre-State sharing. The…
- Under PMGSY (launched 25 December 2000), the original habitation population thresholds for new all-weather road connectivity were:
- A Regional Rural Bank has a paid-up capital of Rs 240 crore held as per the RRB Act 1976 pattern (Centre 50%, State 15%, sponsor bank…
- Which of the following is the sub-target within agriculture for small and marginal farmers (as % of ANBC) under the revised RBI priority…
- Total annual premium of PMSBY (Rs 20) and PMJJBY (Rs 436) is Rs 456. The life cover and accident cover under these two are, respectively: