Quantitative AptitudeVery hardSSC CGL Tier 2 · SSC CPO
A group of men can finish a job in a certain number of days. With 6 more men it would be done 5 days earlier, and with 4 fewer men it would take 5 days longer. How many men are there?
- A. 20
- B. 30
- C. 24
- D. 25
Correct answer: C. 24
nd = (n + 6)(d − 5) gives 6d − 5n = 30; nd = (n − 4)(d + 5) gives 5n − 4d = 20. Adding: 2d = 50, d = 25 and n = 24.
हिंदी में
आदमियों का एक समूह किसी कार्य को कुछ दिनों में पूरा कर सकता है। 6 आदमी अधिक होने पर वह 5 दिन पहले पूरा हो जाता, और 4 आदमी कम होने पर उसमें 5 दिन अधिक लगते। कुल कितने आदमी हैं?
- A. 20
- B. 30
- C. 24
- D. 25
उत्तर: C. nd = (n + 6)(d − 5) से 6d − 5n = 30; nd = (n − 4)(d + 5) से 5n − 4d = 20। जोड़ने पर: 2d = 50, d = 25 और n = 24।
More Time and Work questions
- Ram does 1/3 of a job in 5 days. Shyam then does 2/5 of the remaining work in 4 days, and Mohan finishes the rest in 6 days. How long…
- A and B together can finish a job in 12 days. If A works for 3 days and B for 6 days, 7/20 of the job is done. How long would A take alone?
- A contractor has 30 days to finish a project and employs 50 men working 8 hours a day. After 18 days only 2/5 of the work is done. How…
- A takes 5 days more than B and 9 days more than C to do a job alone. A and B together take as long as C alone. How long does A take alone?
- A is twice as efficient as B, and B is twice as efficient as C. A finishes a job 30 days sooner than C. How long will all three take…
- Pipe A fills a tank in 12 hours and pipe B empties it in 18 hours. Starting with an empty tank, they are opened alternately for one hour…