Quantitative AptitudeHardSSC CGL · SSC CHSL
A does 20% less work than B each day. Together they finish a job in 16 days. How long would B take alone?
- A. 36 days
- B. 32 days
- C. 25.6 days
- D. 28.8 days
Correct answer: D. 28.8 days
A = 0.8 of B's rate, so together = 1.8 B-units. B alone = 16 × 1.8 = 28.8 days.
हिंदी में
A प्रतिदिन B से 20% कम कार्य करता है। साथ मिलकर वे किसी कार्य को 16 दिन में पूरा करते हैं। B अकेला कितना समय लेगा?
- A. 36 दिन
- B. 32 दिन
- C. 25.6 दिन
- D. 28.8 दिन
उत्तर: D. A = B की दर का 0.8, इसलिए साथ में = 1.8 B-इकाई। B अकेला = 16 × 1.8 = 28.8 दिन।
More Time and Work questions
- A patch of water hyacinth doubles its area every day and covers a whole lake at the end of day 10. At the end of which day was half the…
- A, B and C can do a job alone in 10, 15 and 30 days. A and B work together throughout, and C joins them only for the last 2 days. How long…
- A is paid ₹450 a day and can finish a job in 12 days; B is paid ₹300 a day and needs 20 days. Which of them is cheaper for the job, and by…
- An inlet fills a tank in 2 hours and an outlet empties it in 3 hours. The inlet is opened alone, and the outlet is opened too after 1…
- One worker makes 12 toys in 3 hours and another makes 10 toys in 2 hours. Working together 6 hours a day, in how many days will they make…
- 3 men or 6 boys can do a job in 20 days. How long will 2 men and 4 boys take?