A is 25% more efficient than B. If B alone can finish a job in 45 days, in how many days can A and B together finish it?
- A. 18 days
- B. 22½ days
- C. 24 days
- D. 20 days
Correct answer: D. 20 days
A takes 45 ÷ 1.25 = 36 days. Together, 1/45 + 1/36 = 9/180 = 1/20, so the job takes 20 days.
हिंदी में
A, B से 25% अधिक कार्यकुशल है। यदि B अकेला किसी कार्य को 45 दिन में पूरा कर सकता है, तो A और B मिलकर उसे कितने दिन में पूरा करेंगे?
- A. 18 दिन
- B. 22½ दिन
- C. 24 दिन
- D. 20 दिन
उत्तर: D. A को 45 ÷ 1.25 = 36 दिन लगते हैं। साथ मिलकर 1/45 + 1/36 = 9/180 = 1/20, अतः कार्य में 20 दिन लगेंगे।
More Time and Work questions
- The efficiencies of A, B and C are in the ratio 5 : 4 : 3, and together they finish a job in 14 days. In how many days can B and C…
- A is three times as efficient as B, and A takes 18 days less than B to finish a job alone. In how many days can they finish it working…
- A is 50% more efficient than B, and B is twice as efficient as C. If C alone takes 36 days to finish a job, in how many days can A and B…
- A and B together can finish a job in 10 days, and A is 1.5 times as efficient as B. A works alone for 2 days and then leaves, and B…
- A takes 6 days less than B to finish a job alone, and together they finish it in 4 days. In how many days can B alone finish it?
- 15 men working 8 hours a day complete 3/5 of a job in 12 days. How many more men, working 10 hours a day, are needed to finish the rest in…