Quantitative AptitudeModerate
If 6 workers finish a job in 12 days, how many days will 9 workers take at the same rate?
- A. 6
- B. 8
- C. 9
- D. 18
Correct answer: B. 8
Work = 6 × 12 = 72 worker-days, so 9 workers need 72 ÷ 9 = 8 days. 18 assumes days rise with workers (direct proportion), the classic inverse-variation trap.
हिंदी में
यदि 6 कर्मचारी किसी कार्य को 12 दिन में पूरा करते हैं, तो समान दर से 9 कर्मचारी कितने दिन लेंगे?
- A. 6
- B. 8
- C. 9
- D. 18
उत्तर: B. कार्य = 6 × 12 = 72 कर्मचारी-दिन, इसलिए 9 कर्मचारियों को 72 ÷ 9 = 8 दिन लगेंगे। 18 मानता है कि कर्मचारी बढ़ने पर दिन भी बढ़ते हैं (समानुपात), जो व्युत्क्रम अनुपात की सामान्य भूल है।
More Time and Work questions
- A is twice as efficient as B. If together they finish a job in 12 days, A alone would take:
- A can finish a work in 10 days and B in 15 days. Together they finish it in:
- A and B together finish a job in 12 days; A alone takes 20 days. B alone takes:
- A can do a work in 12 days. After working 4 days he leaves and B finishes the rest in 16 days. B alone would take:
- 12 men complete a work in 18 days. After 6 days, 4 more men join. The remaining work is finished in:
- A does one-third of a work in 6 days. He will finish the whole work in: