6 workers can build a wall in 10 days. How many days will 30 workers (working at the same rate) take?

  1. A. 4 days
  2. B. 50 days
  3. C. 15 days
  4. D. 2 days

Correct answer: D. 2 days

Total work = 6 × 10 = 60 man-days. With 30 workers: 60/30 = 2 days.