Quantitative AptitudeHardSSC CGL · RRB NTPC · IBPS
A can do a work in 10 days and B in 40 days. They complete it together and are paid ₹3000. What is A's share?
- A. ₹600
- B. ₹1500
- C. ₹2400
- D. ₹2550
Correct answer: C. ₹2400
Wages are shared in the ratio of work done: A:B = 1/10 : 1/40 = 40:10. A's share = 3000 × 40/50 = 2400.
More Time and Work questions
- A can do a work in 15 days and B in 10 days. They complete it together and are paid ₹3600. What is A's share?
- A, B and C can do a job alone in 8, 12 and 24 days respectively. In how many days will they finish it working together?
- 8 men working 8 hours a day can finish a job in 20 days. If they work only 5 hours a day, how many days will they take?
- Rahul can complete a job in 12 days and Sneha alone can complete it in 6 days. In how many days will they finish it together?
- A can do a piece of work in 15 days. He works for 6 days and leaves. B completes the remaining work in 9 days. In how many days can B…
- 6 workers can build a wall in 12 days. How many days will 9 workers (working at the same rate) take?