6 workers can build a wall in 12 days. How many days will 9 workers (working at the same rate) take?

  1. A. 8 days
  2. B. 10 days
  3. C. 18 days
  4. D. 17 days

Correct answer: A. 8 days

Total work = 6 × 12 = 72 man-days. With 9 workers: 72/9 = 8 days.