6 workers can build a wall in 12 days. How many days will 9 workers (working at the same rate) take?
- A. 8 days
- B. 10 days
- C. 18 days
- D. 17 days
Correct answer: A. 8 days
Total work = 6 × 12 = 72 man-days. With 9 workers: 72/9 = 8 days.