Quantitative AptitudeHardSSC CGL · RRB NTPC · IBPS
A can do a work in 30 days and B in 45 days. They complete it together and are paid ₹2400. What is A's share?
- A. ₹960
- B. ₹1200
- C. ₹1560
- D. ₹1440
Correct answer: D. ₹1440
Wages are shared in the ratio of work done: A:B = 1/30 : 1/45 = 45:30. A's share = 2400 × 45/75 = 1440.
More Time and Work questions
- A can do a work in 20 days and B in 30 days. They complete it together and are paid ₹1200. What is A's share?
- A, B and C can do a job alone in 12, 24 and 8 days respectively. In how many days will they finish it working together?
- 5 men working 8 hours a day can finish a job in 12 days. If they work only 4 hours a day, how many days will they take?
- Meera can complete a job in 30 days and Kavita alone can complete it in 45 days. In how many days will they finish it together?
- Amit can complete a job in 15 days and Sneha alone can complete it in 10 days. In how many days will they finish it together?
- 15 workers can build a wall in 6 days. How many days will 5 workers (working at the same rate) take?