Quantitative AptitudeEasySSC CGL · RRB NTPC · IBPS
Amit can complete a job in 15 days and Sneha alone can complete it in 10 days. In how many days will they finish it together?
- A. 6 days
- B. 12.5 days
- C. 8 days
- D. 25 days
Correct answer: A. 6 days
Together = ab/(a + b) = 15 × 10/25 = 6 days.