A, B and C can do a job alone in 20, 30 and 60 days respectively. In how many days will they finish it working together?

  1. A. 36.67 days
  2. B. 20 days
  3. C. 10 days
  4. D. 11 days

Correct answer: C. 10 days

Combined rate = 1/20 + 1/30 + 1/60 = 0.1 ≈ 1/10 per day, so they need 10 days.