Amit can complete a job in 30 days and Karan alone can complete it in 45 days. In how many days will they finish it together?

  1. A. 18 days
  2. B. 37.5 days
  3. C. 20 days
  4. D. 75 days

Correct answer: A. 18 days

Together = ab/(a + b) = 30 × 45/75 = 18 days.