Quantitative AptitudeModerateSSC CGL · RRB NTPC · IBPS

20 workers can build a wall in 15 days. How many days will 12 workers (working at the same rate) take?

  1. A. 27 days
  2. B. 9 days
  3. C. 25 days
  4. D. 20 days

Correct answer: C. 25 days

Total work = 20 × 15 = 300 man-days. With 12 workers: 300/12 = 25 days.