4 men working 6 hours a day can finish a job in 24 days. If they work only 9 hours a day, how many days will they take?

  1. A. 16 days
  2. B. 21 days
  3. C. 19 days
  4. D. 36 days

Correct answer: A. 16 days

Total work = 4 × 6 × 24 = 576 man-hours. At 9 hours a day, days = 576/(4 × 9) = 16.