4 men working 6 hours a day can finish a job in 24 days. If they work only 9 hours a day, how many days will they take?
- A. 16 days
- B. 21 days
- C. 19 days
- D. 36 days
Correct answer: A. 16 days
Total work = 4 × 6 × 24 = 576 man-hours. At 9 hours a day, days = 576/(4 × 9) = 16.
More Time and Work questions
- A can finish a job in 12 days and B can finish it in 6 days. Working together, they will complete it in:
- A and B together complete a job in 8 days, and A alone can do it in 12 days. B alone would take:
- A, B and C can do a piece of work alone in 10, 15 and 30 days respectively. Working together they will finish it in:
- A and B together can do a work in 18 days, B and C together in 24 days, and A and C together in 36 days. All three working together will…
- A works twice as fast as B. Together they complete a job in 18 days. If A alone works on a second, identical job, the number of days A…
- A can do a job in 20 days and B in 30 days. A works alone for 5 days and then B joins. In how many days in all is the job completed?