A can finish a job in 12 days and B can finish it in 6 days. Working together, they will complete it in:

  1. A. 4 days
  2. B. 9 days
  3. C. 3 days
  4. D. 6 days

Correct answer: A. 4 days

Combined rate = 1/12 + 1/6 = 3/12 = 1/4 per day, so 4 days. Averaging the two times gives 9, which is not how rates combine.