Quantitative AptitudeModerateSSC CGL · IBPS PO pattern

A and B together complete a job in 8 days, and A alone can do it in 12 days. B alone would take:

  1. A. 4 days
  2. B. 20 days
  3. C. 24 days
  4. D. 10 days

Correct answer: C. 24 days

B's rate = 1/8 − 1/12 = 1/24, so 24 days. Subtracting the times (12 − 8 = 4) is the wrong operation.