Quantitative AptitudeHardSSC CGL Tier 2 · IBPS PO Mains

A and B together can do a work in 18 days, B and C together in 24 days, and A and C together in 36 days. All three working together will finish it in:

  1. A. 13 days
  2. B. 18 days
  3. C. 26 days
  4. D. 16 days

Correct answer: D. 16 days

Adding the three pair rates: 1/18 + 1/24 + 1/36 = 9/72 = 1/8 = 2(A + B + C), so A + B + C = 1/16 and the answer is 16 days. Using 1/8 directly (8 days) forgets each worker is counted twice.