Quantitative AptitudeHardSSC CGL Tier 2 · IBPS PO Mains
A and B together can do a work in 18 days, B and C together in 24 days, and A and C together in 36 days. All three working together will finish it in:
- A. 13 days
- B. 18 days
- C. 26 days
- D. 16 days
Correct answer: D. 16 days
Adding the three pair rates: 1/18 + 1/24 + 1/36 = 9/72 = 1/8 = 2(A + B + C), so A + B + C = 1/16 and the answer is 16 days. Using 1/8 directly (8 days) forgets each worker is counted twice.
More Time and Work questions
- A works twice as fast as B. Together they complete a job in 18 days. If A alone works on a second, identical job, the number of days A…
- A can do a job in 20 days and B in 30 days. A works alone for 5 days and then B joins. In how many days in all is the job completed?
- A and B can do a job in 20 and 30 days respectively. They start together but A leaves 4 days before the job is complete. The job takes in…
- A, B and C can do a job in 10, 15 and 30 days. A starts alone; B joins 2 days later, and C joins 2 days after B. The whole job is…
- A and B working together can do a task in 10 days, while A alone can do it in 15 days. They work together for 4 days and then A leaves. B…
- A is three times as efficient as B. If B alone takes 24 days to finish a job, A alone will take: