Quantitative AptitudeModerateSSC CGL · RRB NTPC · IBPS Clerk
A and B working together can do a task in 10 days, while A alone can do it in 15 days. They work together for 4 days and then A leaves. B alone finishes the rest in:
- A. 18 days
- B. 6 days
- C. 15 days
- D. 20 days
Correct answer: A. 18 days
B's rate = 1/10 − 1/15 = 1/30. In 4 days together 2/5 is done, leaving 3/5, which B finishes in 18 days. Using the joint rate for the rest (6 days) ignores that A has left.
More Time and Work questions
- A is three times as efficient as B. If B alone takes 24 days to finish a job, A alone will take:
- A is 25% more efficient than B. If B alone can finish a job in 20 days, A alone can finish it in:
- A is 50% more efficient than B. Together they finish a job in 12 days. A alone will take:
- A is 25% more efficient than B, and B is 20% more efficient than C. If C alone can finish a job in 60 days, A and C working together will…
- 6 men can complete a job in 15 days. To complete it in 10 days, the number of men needed is:
- 15 men can finish a job in 24 days. After 8 days, 5 men leave. The job is then finished after a total of: