6 men can complete a job in 15 days. To complete it in 10 days, the number of men needed is:

  1. A. 4
  2. B. 9
  3. C. 12
  4. D. 7

Correct answer: B. 9

Work = 6 × 15 = 90 man-days; 90/10 = 9 men. 4 would come from wrongly scaling days directly.