Quantitative AptitudeVery hardSSC CGL · RRB NTPC · IBPS Clerk

8 men and 12 women can finish a job in 10 days, and 6 men and 8 women can finish it in 14 days. One woman working alone will finish it in:

  1. A. 280 days
  2. B. 140 days
  3. C. 210 days
  4. D. 350 days

Correct answer: A. 280 days

Equate the work: 10(8m + 12w) = 14(6m + 8w), so 80m + 120w = 84m + 112w and m = 2w. Work = 10 × 28w = 280 woman-days, so 280 days. 140 days is the time for one man.