A can do a job in 6 days and B in 9 days. They finish it together and are paid ₹4,500. A's share is:

  1. A. ₹1,800
  2. B. ₹2,700
  3. C. ₹2,250
  4. D. ₹3,000

Correct answer: B. ₹2,700

Their work ratio equals the efficiency ratio 1/6 : 1/9 = 3 : 2, so A gets 3/5 of 4,500 = ₹2,700. ₹1,800 is B's share.