Quantitative AptitudeHardSSC CGL Tier 2 · IBPS PO Mains

A can do a job in 10 days and B in 12 days. They work on alternate days, B starting first. The job is completed in:

  1. A. 10 days
  2. B. 11.5 days
  3. C. 12 days
  4. D. 11 days

Correct answer: D. 11 days

Each pair of days does 1/10 + 1/12 = 11/60. After 5 pairs (10 days) 55/60 is done, and B (1/12 = 5/60 per day) finishes it on day 11. Dividing 11/60 into 1 gives about 5.45 pairs, which is not the day count.