A can finish a piece of work in 12 days and B in 18 days. Working together, they will finish it in

  1. A. 7.2 days
  2. B. 7 days
  3. C. 7.5 days
  4. D. 6.5 days

Correct answer: A. 7.2 days

Together they do 1/12 + 1/18 = 5/36 of the work per day, so they need 36/5 = 7.2 days.