15 men can complete a work in 24 days. The number of days 20 men will take to do the same work is

  1. A. 20 days
  2. B. 16 days
  3. C. 18 days
  4. D. 32 days

Correct answer: C. 18 days

Total work = 15 × 24 = 360 man-days, so 20 men need 360/20 = 18 days.