Quantitative AptitudeModerateSSC CGL · SBI Clerk

A completes 1/3 of a work in 5 days and B completes 2/5 of the same work in 6 days. Working together, they will complete the whole work in

  1. A. 7.5 days
  2. B. 6 days
  3. C. 8 days
  4. D. 5 days

Correct answer: A. 7.5 days

A alone needs 15 days and B alone needs 15 days. Together, 1/15 + 1/15 = 2/15 per day, so 7.5 days.