A and B can do a job in 12 and 18 days respectively. They begin together, but A leaves 4 days before the work is completed. The job is completed in
- A. 8 days
- B. 9 days
- C. 10.4 days
- D. 9.6 days
Correct answer: D. 9.6 days
B works all T days and A works T − 4 days: (T − 4)/12 + T/18 = 1 gives 5T = 48, so T = 9.6 days.
More Time and Work questions
- A can do a job in 12 days and B in 15 days. They work on alternate days, A starting first. The job is completed in
- A, B and C can do a job in 10, 15 and 30 days. They finish it together and are paid ₹4,800 in all. C's share is
- 24 men can complete a job in 30 days. After 10 days, 8 men leave. The whole job is finished in a total of
- A pipe fills a tank in 8 hours. Because of a leak at the bottom it takes 2 hours longer. The leak alone can empty the full tank in
- Pipes A and B can fill a tank in 10 and 15 hours, and pipe C can empty it in 20 hours. If all three are opened together, the empty tank is…
- A is 25% more efficient than B. If A alone can finish a job in 20 days, A and B together will finish it in