24 men can complete a job in 30 days. After 10 days, 8 men leave. The whole job is finished in a total of

  1. A. 35 days
  2. B. 45 days
  3. C. 40 days
  4. D. 38 days

Correct answer: C. 40 days

Total work = 720 man-days; after 10 days 480 remain and 16 men take 30 days, so the total is 40 days.