A can do a work in 24 days and B in 40 days. They work together for 6 days and then B leaves. A will finish the remaining work in

  1. A. 14.4 days
  2. B. 12 days
  3. C. 15 days
  4. D. 18 days

Correct answer: A. 14.4 days

In 6 days they complete 6 × (1/24 + 1/40) = 2/5, so 3/5 remains, and A needs 3/5 × 24 = 14.4 days.