Quantitative AptitudeVery hardSBI PO · SSC CGL
A, B and C can do a job in 12, 18 and 36 days. All three start together, but C leaves after 4 days. The job is completed in
- A. 6 days
- B. 6.4 days
- C. 7 days
- D. 5.5 days
Correct answer: B. 6.4 days
In 36ths: 3, 2, 1 per day. In 4 days 24 units are done, leaving 12 that A and B (5 per day) finish in 2.4 days. Total 6.4 days.
More Time and Work questions
- A is 25% more efficient than B, and C is 25% less efficient than B. If A alone can complete a job in 24 days, A, B and C together will…
- An empty cistern can be filled by pipe A in 20 hours and emptied by pipe B in 30 hours. A is kept open for 1 hour, then B for 1 hour…
- A and B can do a job in 20 and 30 days. They work together for some days; then A leaves and B completes the rest of the work in 10 more…
- 15 men working 8 hours a day complete 2/5 of a job in 12 days. The remaining work is to be finished by 10 men working 9 hours a day. The…
- If A can do a piece of work in 8 days, the fraction of work A does in one day is:
- If 6 workers finish a job in 12 days, how many days will 9 workers take at the same rate?