Quantitative AptitudeVery hardSSC CGL Tier 2 · SBI PO

15 men working 8 hours a day complete 2/5 of a job in 12 days. The remaining work is to be finished by 10 men working 9 hours a day. The number of days they need is

  1. A. 20 days
  2. B. 24 days
  3. C. 28 days
  4. D. 30 days

Correct answer: B. 24 days

The whole job is 15 × 8 × 12 ÷ (2/5) = 3600 man-hours, leaving 2160; 10 men at 9 hours a day give 90 man-hours daily, so 24 days.