Quantitative AptitudeVery hardSSC CGL Tier 2 · IBPS PO
A is 25% more efficient than B, and C is 25% less efficient than B. If A alone can complete a job in 24 days, A, B and C together will complete it in
- A. 8 days
- B. 12 days
- C. 10 days
- D. 9.6 days
Correct answer: C. 10 days
Efficiencies A : B : C = 5 : 4 : 3, so together 12 units per day. A needs 24 days for 120 units, so all three need 120/12 = 10 days.
More Time and Work questions
- An empty cistern can be filled by pipe A in 20 hours and emptied by pipe B in 30 hours. A is kept open for 1 hour, then B for 1 hour…
- A and B can do a job in 20 and 30 days. They work together for some days; then A leaves and B completes the rest of the work in 10 more…
- 15 men working 8 hours a day complete 2/5 of a job in 12 days. The remaining work is to be finished by 10 men working 9 hours a day. The…
- If A can do a piece of work in 8 days, the fraction of work A does in one day is:
- If 6 workers finish a job in 12 days, how many days will 9 workers take at the same rate?
- A is twice as efficient as B. If together they finish a job in 12 days, A alone would take: