Quantitative AptitudeVery hardSBI PO · IBPS PO

A, B and C can do a job alone in 20, 25 and 50 days respectively. They work one day each in the order A, B, C, A, B, C, ... The job is completed in

  1. A. 27 days
  2. B. 28 days
  3. C. 29 days
  4. D. 30 days

Correct answer: B. 28 days

In units of 1/100: A does 5, B does 4, C does 2, so 11 per 3-day cycle. After 27 days 99 are done and A completes the last unit on day 28.