Quantitative AptitudeVery hardIBPS PO · SSC CGL Tier 2

A work can be done by 30 men in 20 days. 30 men work for the first 5 days, then 10 men leave, and after another 5 days 5 additional men join the remaining workers. The total number of days to finish the work is

  1. A. 24 days
  2. B. 22 days
  3. C. 25 days
  4. D. 26 days

Correct answer: A. 24 days

Work = 600 man-days. 5 days × 30 = 150 and 5 days × 20 = 100 leave 350; with 25 men that is 14 more days, so 24 days in all.