Quantitative AptitudeVery hardIBPS PO · SSC CGL Tier 2
A work can be done by 30 men in 20 days. 30 men work for the first 5 days, then 10 men leave, and after another 5 days 5 additional men join the remaining workers. The total number of days to finish the work is
- A. 24 days
- B. 22 days
- C. 25 days
- D. 26 days
Correct answer: A. 24 days
Work = 600 man-days. 5 days × 30 = 150 and 5 days × 20 = 100 leave 350; with 25 men that is 14 more days, so 24 days in all.
More Time and Work questions
- A, B and C can do a job in 12, 18 and 36 days. All three start together, but C leaves after 4 days. The job is completed in
- A is 25% more efficient than B, and C is 25% less efficient than B. If A alone can complete a job in 24 days, A, B and C together will…
- An empty cistern can be filled by pipe A in 20 hours and emptied by pipe B in 30 hours. A is kept open for 1 hour, then B for 1 hour…
- A and B can do a job in 20 and 30 days. They work together for some days; then A leaves and B completes the rest of the work in 10 more…
- 15 men working 8 hours a day complete 2/5 of a job in 12 days. The remaining work is to be finished by 10 men working 9 hours a day. The…
- If A can do a piece of work in 8 days, the fraction of work A does in one day is: