A, B and C can complete a job in 10, 15 and 30 days respectively. A and B start the work; C joins them after 2 days and A leaves after 5 days from the start. B and C then finish the job. The total time taken is
- A. 5 1/3 days
- B. 6 days
- C. 5 2/3 days
- D. 5 days
Correct answer: C. 5 2/3 days
In units of 1/30: A, B, C do 3, 2, 1 per day. Days 1–2 give 10, days 3–5 give 18, total 28; the remaining 2 units at 3 per day take 2/3 day. Total 5 2/3 days.
More Time and Work questions
- Pipe A fills an empty tank in 12 hours and pipe B fills it in 20 hours, while pipe C empties the full tank in 30 hours. A and B are opened…
- A work can be done by 30 men in 20 days. 30 men work for the first 5 days, then 10 men leave, and after another 5 days 5 additional men…
- A, B and C can do a job in 12, 18 and 36 days. All three start together, but C leaves after 4 days. The job is completed in
- A is 25% more efficient than B, and C is 25% less efficient than B. If A alone can complete a job in 24 days, A, B and C together will…
- An empty cistern can be filled by pipe A in 20 hours and emptied by pipe B in 30 hours. A is kept open for 1 hour, then B for 1 hour…
- A and B can do a job in 20 and 30 days. They work together for some days; then A leaves and B completes the rest of the work in 10 more…