4 men and 6 women can complete a job in 8 days, while 3 men and 7 women can complete it in 10 days. 10 women working together will complete it in

  1. A. 50 days
  2. B. 30 days
  3. C. 36 days
  4. D. 40 days

Correct answer: D. 40 days

8(4m + 6w) = 10(3m + 7w) gives m = 11w. The work is 8 × 50w = 400w, so 10 women take 40 days.