Quantitative AptitudeHardSSC CGL · IBPS PO
4 men and 6 women can complete a job in 8 days, while 3 men and 7 women can complete it in 10 days. 10 women working together will complete it in
- A. 50 days
- B. 30 days
- C. 36 days
- D. 40 days
Correct answer: D. 40 days
8(4m + 6w) = 10(3m + 7w) gives m = 11w. The work is 8 × 50w = 400w, so 10 women take 40 days.
More Time and Work questions
- A can do a work in 24 days and B in 40 days. They work together for 6 days and then B leaves. A will finish the remaining work in
- A, B and C can do a job alone in 20, 25 and 50 days respectively. They work one day each in the order A, B, C, A, B, C, ... The job is…
- A, B and C can complete a job in 10, 15 and 30 days respectively. A and B start the work; C joins them after 2 days and A leaves after 5…
- Pipe A fills an empty tank in 12 hours and pipe B fills it in 20 hours, while pipe C empties the full tank in 30 hours. A and B are opened…
- A work can be done by 30 men in 20 days. 30 men work for the first 5 days, then 10 men leave, and after another 5 days 5 additional men…
- A, B and C can do a job in 12, 18 and 36 days. All three start together, but C leaves after 4 days. The job is completed in