A can do a job in 12 days and B in 15 days. They work on alternate days, A starting first. The job is completed in

  1. A. 14 days
  2. B. 13 days
  3. C. 15 days
  4. D. 12 days

Correct answer: A. 14 days

A pair of days does 9/60 = 3/20. After 12 days, 9/10 is done; day 13 (A) adds 5/60, leaving 4/60, which B finishes on day 14.