Quantitative AptitudeModerateSSC CHSL · IBPS Clerk
A can do a job in 20 days. He works for 5 days and then B completes the rest in 9 days. B alone can do the whole job in
- A. 15 days
- B. 12 days
- C. 18 days
- D. 9 days
Correct answer: B. 12 days
A does 1/4 of the job; B does the remaining 3/4 in 9 days, so B alone needs 9 ÷ (3/4) = 12 days.
More Time and Work questions
- 15 men can complete a work in 24 days. The number of days 20 men will take to do the same work is
- A pipe fills a tank in 6 hours and another pipe empties the full tank in 9 hours. If both are opened together, the empty tank will be…
- Two pipes can fill a tank in 12 hours and 15 hours respectively. Opened together, they fill it in
- A is twice as efficient as B. Together they finish a job in 12 days. B alone would finish it in
- A can do a job in 12 days and B in 18 days. They are paid a total of ₹4,500 for the job and share the wages in proportion to the work…
- 5 men can complete a work in 12 days. The number of days 8 men will take to complete the same work is