A job needs 156 man-days of work. On day 1, 2 men work; each day 2 more men join than the day before (2, 4, 6, ...). The number of days to finish is:

  1. A. 13 days
  2. B. 12 days
  3. C. 11 days
  4. D. 10 days

Correct answer: B. 12 days

After n days the work is 2 + 4 + ... + 2n = n(n + 1). For 156, n = 12 (12 × 13). n = 11 gives only 132.