Quantitative AptitudeModerateSSC CGL · IBPS PO pattern
A job needs 156 man-days of work. On day 1, 2 men work; each day 2 more men join than the day before (2, 4, 6, ...). The number of days to finish is:
- A. 13 days
- B. 12 days
- C. 11 days
- D. 10 days
Correct answer: B. 12 days
After n days the work is 2 + 4 + ... + 2n = n(n + 1). For 156, n = 12 (12 × 13). n = 11 gives only 132.
More Time and Work questions
- A can finish a piece of work in 12 days and B in 18 days. Working together, they will finish it in
- A can do a job in 20 days. He works for 5 days and then B completes the rest in 9 days. B alone can do the whole job in
- 15 men can complete a work in 24 days. The number of days 20 men will take to do the same work is
- A pipe fills a tank in 6 hours and another pipe empties the full tank in 9 hours. If both are opened together, the empty tank will be…
- Two pipes can fill a tank in 12 hours and 15 hours respectively. Opened together, they fill it in
- A is twice as efficient as B. Together they finish a job in 12 days. B alone would finish it in