A can finish a task in 10 days and B in 15 days. They work on alternate days, A starting first. The task will be finished in:

  1. A. 6 days
  2. B. 15 days
  3. C. 12 days
  4. D. 13 days

Correct answer: C. 12 days

Each pair of days completes 1/10 + 1/15 = 1/6, so 6 pairs = 12 days. 6 days would be the time if both worked every day together.